|
Nearly all litigation matters handled by the firm result in
settlement on confidential terms. For this reason, and to protect
client confidentiality, non-public results are not published.
Following is a list of public results in trials, arbitrations and
mediations.
West Coast Air Conditioning Co., Inc. v. Fountain Valley School
District (Construction)
Orange County Superior Court Case No. 07CC05300
2008: Prime contractor on four school modernization project
suffered delay, disruption and inefficiency damages as a result
of unclear plans and specifications, and late completion of
predecessor activities by other contractors to the District.
The Firm filed suit to collect the damages. Following over a
year of litigation and cordial meetings with the District, its
counsel and experts to explain the claim, the case was mediated
to a settlement with the Firm’s client being paid 1.275 million
for delay and disruption damages, and receiving a thank you
letter from the District for building a quality construction
project.
Counsel:
P.
Randolph Finch Jr., Justin
M. Stoger
and Dustin R. Jones
Johnson, Barnes & Finch, Inc. v. Meier Pacific, Inc., et al.
(Construction)
San Diego Superior Court Case No. GIC881652
2008: Numerous subcontractors initiated litigation against
Firm’s general contractor client and the project owner to
collect subcontract balances. The Firm’s general contractor
client asserted the pass through claims for unpaid contract
balance and for additional overhead to build the project, which
was completed over one year behind schedule. The project owner
countered with a delay claim and other claims. Through a series
of negotiations, settlement conferences and mediation just prior
to a jury trial, the Firm’s client was paid on its claim for
additional compensation, and received full indemnity from the
owner for all subcontractor suits.
Counsel:
Davide
Golia
and
Nowell A. Lantz
GBC Concrete and Masonry, Inc. v. Altadena Lincoln Crossing,
LLC, et al. (Construction)
Los Angeles Superior Court Case No. GC037960
2008: Firm’s trade contractor client sued project owner and
lender to recover $311,000.00 for improvements to the project.
The Firm’s client’s early litigation offer to accept $336,000.00
was rebuked by the defendant. After obtaining a pre-judgment
writ of attachment and summary adjudication of its breach of
contract and lien foreclosure causes of action, and attaching
rents due the project owner, the case settled with the Firm’s
client being paid $475,000.00.
Counsel:
P.
Randolph Finch Jr.
and
Andrea L. Petray
Protest of Award to HAR Construction by Jaynes
Corporation of California
(Construction)
Southwestern Community College District Higher Education Center
at San Ysidro, Project No. 20702-E-01
2008: This matter involved the award of a $4 million
educational building project by the Southwestern Community
College District. Based on an irregularity in the low bidder’s
bid amount, the Firm successfully protested and the District
rejected the low bid and awarded the project to the Firm’s
client after two public hearings conducted by the District to
consider the matter.
Counsel:
P.
Randolph Finch Jr.
and Dustin R. Jones
Protest of Award to W.E. O’Neil Construction Co. by Jaynes
Corporation of California
(Construction)
Eastern Municipal Water District Administrative Office Building
Expansion
2008: The Firm protested award of a $19 million office building
project by the Eastern Municipal Water District based on
inconsistencies in the low bidder’s subcontractor listing. The
District responded by rejecting all bids and on rebid, the water
district revised its bidding instructions to eliminate
ambiguities pointed out by the Firm. The Firm’s client was the
low bidder and awarded the contract following the rebid.
Counsel:
P.
Randolph Finch Jr.
and Dustin R. Jones
Plasterers, Local 200 (Standard Drywall, Inc.)
(Labor)
National Labor Relations Board
Case No. 21-CD-659
2008: Local 200 of the Plasterers’ union filed two state
court lawsuits against the Firm’s client, which is signed to a
collective-bargaining agreement with the Carpenters’ union.
Local 200’s lawsuits seek injunctive relief, compensatory
damages, punitive damages, and restitution. Unfair labor
practice charges were filed against Local 200 under section
8(b)(4)(D) of the NLRA. The charges allege the real motive
behind the lawsuits is to force a reassignment of plastering
work to Local 200’s members instead of continuing to assign that
work to employees represented by the Carpenters’ union. An NLRB
administrative law judge agreed. He ordered the lawsuits be
dropped and that the Firm’s client be reimbursed for its
attorneys’ fees.
Counsel: Stephen J. Schultz
and Mark T. Bennett
Blackinton Airport Property Owners Association v. Dino DeLuca,
et al. (Real Estate)
San Diego Superior Court Case
No. GIN0056722
2008: Plaintiff homeowners association sued to foreclose on a
lien to collect delinquent assessments in the amount of
$154,000.00. Defendant asserted a cross-claim for declaratory
relief seeking to invalidate the homeowners association’s
allocation of airport landing rights. After the second day of
plaintiff’s case-in-chief at trial, and testimony by sitting
Justice MacDonald (who drafted the operating documents for the
association), defendant agreed to pay the full amount of the
lien plus $150,000.00 in attorneys’ fees and costs; and judgment
validating the allocation of landing rights.
Counsel: Jason R. Thornton and
Andrea L. Petray
Protest of Award to Gamut Construction Company, Inc. by Jaynes
Corporation of California (Construction)
City of Escondido Fire Station No. 1
2007: The Firm protested award of a $12 million fire station
project on the basis of an irregularity in the low bidder’s bid
bond. The Firm succeeded and the City Council rejected the low
bid and awarded the project to the Firm’s client despite a
significant bid spread.
Counsel:
P.
Randolph Finch Jr.
and
Dustin R. Jones
Time And Alarm Systems v. Edge Development, Inc., et al.
(Construction)
San Bernardino Superior Court
Case No. SCVSS 143134
2007: Second-tier subcontractor initiated litigation to
collect contract balance on a 42 million dollar new High School
project which was completed over one year behind schedule with
delay and disruption claims by more than a half dozen
subcontractors totaling over 8 million dollars. After serving as
project counsel since 2004, the Firm represented the general
contractor in responding to the subcontractor claims and
pursuing the owner for payment of the legitimate amount of the
same, as well as the additional costs of the general contractor.
Through a series of liquidation agreements, mediations and
negotiations with the owner and its counsel, the Firm’s client
avoided liability to the subcontractor claimants beyond the
amount paid by the owner, and recovered additional compensation
for its work, with the District paying the Firms’ client over
2.6 million dollars to resolve the consolidated law suits.
Counsel:
P.
Randolph Finch Jr.
and Andrea L. Petray
John
Zayak v. John
T. Hardisty Construction, Inc., et al. (Business)
San Diego
Superior Court Case No.GIC852090
2007: Plaintiff sued to collect $90,000
owed by defendants under a promissory note. Defendants asserted
cross-claims for breach of fiduciary duty, fraud and
conversion. On the eighth day of a ten day jury trial,
defendants agreed to dismiss their claims, and pay plaintiff
$140,000 plus attorneys’ fees and costs in settlement of the
action. After the court awarded fees and costs, plaintiff’s
total recovery
was $429,223.11.
Counsel: Davide
Golia and Bernard F. King III
Rossi Concrete, Inc. (Labor
and Employment)
2007: 21-RC-20948
The Southern California District
Council of Laborers filed an election petition with the
National Labor Relations Board. The Union sought to represent a
bargaining unit comprised of all the company's field construction
employees, including its foremen. The firm successfully argued the
foremen were supervisors, must be excluded from the bargaining unit,
and could not vote in the election. The union lost the election 49
to 19.
Counsel: Stephen J. Schultz
Sandra Hillagoss, et al. v. Fish & Fish Real Estate, Inc., et al. (Personal Injury)
San Diego County Superior Court Case No.
GIC852635
2007: Mediation of trip and
fall shoulder injury claim resulting in $400,000 settlement in
favor of firm's client
Counsel: Christina M. Rimkus
Southwest Regional Council of Carpenters (Standard Drywall, Inc. ) (Labor and Employment)
348 NLRB No. 87
2006:
This case involved a proceeding under section 10(k) of the National
Labor Relations Act. The firm successfully defended the client’s
right to assign plastering work on all Southern California public
works projects to employees represented by the Carpenters union
instead of to employees represented by the Plasterers union. The
NLRB agreed with the firm that the client did not have to submit the
work assignment issue to the AFL-CIO’s Plan for Resolution of
Jurisdictional Disputes.
Counsel:
Mark T. Bennett
Kims v. Rowley, et al
(Construction)
San Diego County Superior Court
Case No. GIC 845277
2006: Two week jury trial regarding private work of improvement
resulting in 9-3 defense verdict in favor of firm's client on
complaint seeking disgorgement of over $800,000 for alleged
unlicensed contractor work. Last pre-trial offer by firm’s
client was to pay $5,000 to settle.
Counsel:
Davide Golia and Nowell A. Lantz
Global Conveyance, Inc., et al. v. Roel Construction Co., Inc., et
al. (Business)
San Diego County Superior Court
Case No. GIC831566
2006: Eight day bench trial
on complaint against client seeking $90 million, plus punitive
damages, resulting in complete defense judgment in favor of
firm's contractor client. Plaintiff’s last pre-trial offer was
to accept payment of $15 million.
Counsel:
Davide Golia and Louis J. Blum
J.B. Riha Corporation v. Andrew and
Mary Connors-Nicholls (Construction)
San Diego County Superior Court
Case No. GIC841028
2006: Three week jury trial
regarding private work of improvement resulting in 11-0 verdict
in favor of firm's contractor client on complaint, zero recovery
on $1,000,000 cross-complaint of property owner opponent
(including claims for punitive damages) against both contractor
and project manager.
Counsel:
Davide Golia and Nowell A. Lantz
Southwest Regional Council of
Carpenters (Standard Drywall, Inc.) (Labor and Employment)
346 NLRB No. 48
2006: Two day NLRB hearing in
which the firm successfully defended its client’s right to assign
plastering work to employees represented by the Carpenters union
instead of to employees represented by the Plasterers’ union. The
Plasterers’ union’s state court lawsuit was deemed to be a claim
to the plastering work.
Counsel:
Mark T. Bennett
First Class Water and Shower v. B.
L. Murphy, dba B. L. Murphy & Sons (Business)
San Diego Superior Court Case No.
GIC840592
2006: Two week jury trial
regarding breach of contract and conversion resulting in 10-2
verdict in favor of firm's client on plaintiff's complaint and 12-0
verdict in favor of firm's client on its cross-complaint.
Counsel:
Davide Golia and David W. Smiley
Roel Construction Co., Inc. v.
Fladeboe Automotive Group, Inc., et al. (Construction)
Orange County Superior Court Case No.
04CC05399
2005: Three week jury trial
regarding private work of improvement resulting in 12-0 verdict in
favor of firm's contractor client on complaint, zero recovery
on cross-complaint of property owner opponent, and declaration that
termination was for convenience not cause.
Counsel:
Davide Golia and Louis J. Blum
Arnco Construction, Inc. v. Douglas
E. Barnhart, Inc., et al. (Construction)
Ventura Superior Court (Central) Case
No. CIV225522;
Second District Court of Appeal Case
No. B187192
2005: Bench trial of claims by
subcontractor for compensation by general contractor resulting in
judgment in favor of firm's general contractor client including
award of attorneys’ fees and costs against the subcontractor
plaintiff of over five times the amount sought by plaintiff.
2006: Judgment affirmed by the court
of appeals, and client awarded costs on appeal.
Counsel:
Robert J. Marks, P.
Randolph Finch Jr. and Rachel F. Tait
Valley Coast Construction, Inc. v.
City of El Cajon (Construction)
American Arbitration Association Case
No. 73 110 133 04 OLTR
2005: Six day arbitration regarding
public work of improvement resulting in judgment in favor of firm's
contractor client on complaint against public agency
owner, including award of attorneys’ fees and costs pursuant
to Public Contract Code section 7107 and Code of Civil Procedure
section 1021.5, and determination of wrongful
withholding of retention.
Counsel:
Robert J. Marks and Chad T. Wishchuk
Oakwood Remodeling & Construction,
Inc. v. Symmetry Cabinet Company
(Construction Litigation)
American Arbitration Association Case
No. 73 110 E 00472 04 CHPA
2005: Two day arbitration regarding
private work of improvement resulting in judgment in favor of
firm's contractor client on complaint, and zero recovery on cross-complaint
by subcontractor opponent.
Counsel:
Jeffrey B. Baird and Christina M.
Rimkus
Los Angeles Testing Engineers, Inc.
v. DMJM International (Business)
Orange County Superior Court Case No.
03CC1102/ JAMS Arbitration No. 1200035911
2005: Three day arbitration regarding
contract interpretation resulting in judgment in favor of
firm's professional services client on complaint for $481,179.
Counsel:
Robert J. Marks
Earth Patterns v.
Garville, et al. (Construction)
Orange County Superior Court Case No.
03CC15063
2004: Two day arbitration regarding
private work of improvement resulting in judgment in favor of
firm's contractor client on complaint and zero recovery on cross-complaint
by property owner opponent for over $250,000.
Counsel: P.
Randolph Finch Jr. and Christina M.
Rimkus
Nick Pecoraro Painting &
Decorating, Inc. v. PCL Construction Services, Inc., et al.
(Construction)
Los Angeles Superior Court, West
District Case No. SC074509
2003: Seven day bench trial regarding
private work of improvement resulting in judgment in favor of
firm's subcontractor client on complaint, and zero
recovery on cross-complaint by general contractor opponent.
Counsel:
Davide Golia, Jeffrey B. Baird and
Louis J. Blum
Straub Construction, Inc. v. R & J
Sheet Metal, Inc. (Construction)
American Arbitration Association No.
73 M 110 333 99 JF
2003: Six day arbitration
regarding federal work of improvement resulting in judgment in favor
of firm's contractor client on complaint, and zero
recovery on cross-complaint by subcontractor opponent.
Counsel: Robert
J. Marks
|